    Planning a Kitchen Renovation in London or St. Thomas: Permits, Trades and the Order of Work

    Do you need a permit to redo a kitchen in London or St. Thomas? Sometimes. Here's what the City of London's own list says, where the Electrical Safety Authority comes in, and the order a kitchen job should happen in.

    P

    Paragon Refacing Team

    Kitchen Renovation Experts

    Share:
    Modern white kitchen with island seating and stainless steel appliances

    Planning a kitchen renovation is mostly deciding what order to do things in, and what to check before you do any of them. The fun part, picking colours, comes later. (We know. We also wanted to start with the colours.)

    Short answer: decide whether your kitchen's problem is looks or function, pick the level of work that fixes it, check whether that work needs a building permit or an electrical notification, then measure, order and install in the right order. In London, cabinets alone don't need a building permit. Moving a sink, adding a kitchen exhaust or altering walls does.

    The rules below were checked against the City of London, the City of St. Thomas and the Electrical Safety Authority in November 2026. Rules change, and your project's details matter, so confirm with the city before work starts. This is a guide, not legal advice.

    Step 1: Decide what's actually wrong

    Write down what bothers you about the kitchen. Then sort the list into two piles:

    • How it looks: dated doors, tired countertop, colours from another era
    • How it works: not enough storage, bad workflow, no room for two people

    If everything is in the first pile, you probably don't need a renovation that moves anything. Refacing and a countertop may do it. If the second pile is long, you're planning new cabinets, maybe a new layout. That one decision sets your budget, your timeline and whether permits come into it.

    Step 2: Check the permits

    In London

    The City of London's before you apply for a building permit page lists what does and doesn't need a permit. For kitchens, the useful lines are:

    No building permit needed (from the City's list):

    • "Cabinetry or cupboards"
    • "Painting"
    • "Plumbing fixture replacement: In the same location (e.g., sink, tub, toilet, shower)"

    Building permit needed (from the City's list):

    • "Plumbing fixtures: Adding, removing, or relocating sinks, tubs, toilets, or showers"
    • "Kitchen exhaust"
    • "Interior alterations"
    • "Doors: Adding new or enlarging existing doors"

    In plain terms: new cabinets or refaced cabinets in the same layout, with the sink staying put, normally don't need a building permit in London. Moving the sink, adding a range hood that vents through the house, or opening up a wall normally does.

    In St. Thomas

    The City of St. Thomas building permits page says building permits are required for the construction or alteration of buildings, including plumbing works, and that "it is the building and or property owner's responsibility to ensure that a building permit is obtained when required." It doesn't publish a kitchen-by-kitchen list the way London does. If your plan touches plumbing or walls, call St. Thomas Building Services first.

    Elsewhere in Elgin, Middlesex and Oxford

    Townships and towns around London and St. Thomas run their own building departments. Same advice: if plumbing or walls move, ask before you start.

    Step 3: Electrical has its own rules

    A building permit and electrical approval are two different things. The Electrical Safety Authority says almost all electrical work must be reported by filing a notification of work, and that having a building permit "isn't the same as filing an electrical notification. You may need both."

    Who does it matters too. ESA says that if you hire someone to do electrical work in your home, by law it must be a Licensed Electrical Contractor, and they file the notification. Homeowners can do electrical work in their own home but still have to file it themselves.

    New pot lights, under-cabinet lighting, a moved range circuit, outlets in a new island: all electrical work. Plan for it.

    Step 4: Measure, design, then order

    Nothing project-specific should be ordered until final measurements are taken in the actual kitchen. Older homes in both cities are rarely perfectly square, and a drawing doesn't know that the floor dips by the back door.

    For custom kitchens, this is also when a 3D design pays for itself. Moving an island on screen is free. Moving it in your kitchen is not.

    Step 5: The order of work

    For a renovation with new cabinets, the usual order is:

    1. Demolition and removal of old cabinets
    2. Plumbing and electrical rough-in, with inspections where required
    3. Drywall and any wall repairs
    4. Flooring, if it runs under the cabinets
    5. Cabinet installation, levelled and secured
    6. Countertop templating on the installed cabinets
    7. Countertop installation, sink and faucet hookup
    8. Backsplash, hardware, final electrical and adjustments

    Step 6 trips people up. Countertops should be measured on the installed, level cabinets, not from the plan. That's how they end up fitting the kitchen you have.

    For a refacing job the list is much shorter: prep the boxes, cover the visible surfaces, hang the new doors and drawer fronts, adjust, install hardware. Most standard refacing jobs take 3 to 5 days, and there's no demolition step. Our refacing process guide has the day-by-day.

    Step 6: Plan how you'll live through it

    For a full renovation, set up a temporary kitchen somewhere else in the house: microwave, kettle, a table, paper plates. You will become very good at making toast. For refacing, the sink, counters and appliances stay in service, so it's mostly a few days of cabinets without doors.

    Rule of thumb

    If your plan doesn't move the sink, the stove or a wall, it's simpler, cheaper and usually permit-free in London. Every time something moves, add a trade, a permit check and some time.

    Once you know the level of work, what a kitchen renovation costs in London and St. Thomas is the next question. When you're ready, we do kitchen cabinets in St. Thomas, kitchen refacing in London and everything in between, starting with a free in-home estimate. We'll bring the tape measure. You bring the list of what's bugging you.

    Frequently Asked Questions

    Not for the cabinets themselves. The City of London lists cabinetry or cupboards among projects that don't need a building permit. Moving a sink, adding a kitchen exhaust or altering walls does need one.
    In London, refacing falls under cabinetry, which the City lists as not needing a building permit. In St. Thomas or another municipality, check with the local building department if your project changes plumbing or walls.
    In Ontario, the person doing the electrical work files a notification of work with the Electrical Safety Authority. If you hire someone, it must be a Licensed Electrical Contractor, and they file it.
    After the base cabinets are installed and level. Measuring countertops off a drawing instead of the installed cabinets is how gaps and overhangs happen.

    Ready to Get Started?

    Get a free consultation and detailed quote for your kitchen project. Our team is ready to bring your vision to life.

    Schedule Your Free Consultation
    Tags:planning a kitchen renovationhow to kitchen renovationdo you need a permit for a kitchen renovation in ontariokitchen renovation permit london ontariodo i need a permit to replace kitchen cabinets

    Related Articles

    Continue exploring our kitchen renovation guides